HCM City’s “record” bridge to open this week

Published: 30/08/2010 05:00

0

252 views

The 104 meter long Hoang Hoa Tham Bridge will be put into operation on September 1. This short bridge holds a national record for construction time: 12 years. The 104 meter long Hoang Hoa Tham Bridge, which links Binh Thanh District and District 1, will be put into operation on September 1. This short bridge holds a national record for construction time: 12 years.

This bridge crosses Nhieu Loc-Thi Nghe canal. Once it opens for traffic, it will help ease traffic on streets like Dinh Tien Hoang, Vo Thi Sau, Hai Ba Trung, etc.

Construction on this bridge began in September 1998 with initial capital of only 19 billion dong. According to plan, it would have been finished in 16 months but actually, it has taken 12 years and three investors.

Total investment increased from 19 to 155 billion dong ($8.15 million).

PV

Provide by Vietnam Travel

HCM City’s “record” bridge to open this week - Social - News |  vietnam travel company

You can see more



enews & updates

Sign up to receive breaking news as well as receive other site updates!

Ads by Adonline